Emmerson Lumber is considering development of electricity generation at an existing dam on the Drag River in Haliburton. This report performs a cursory examination of two of the biggest issues surrounding the proposed development project: engineering/costs and the possible environmental impacts. It lays the groundwork for a pre-feasibility study, and for further assessments beyond this level.

Topics covered are a description of the planned site, engineering and design, environmental assessment, modification, mitigation, and compensation. General recommendations conclude the report.]]>
Host contact: Emmerson, Kim]]> Department: Environmental and Resource Science/Studies]]>

The proposed hydropower development would be run-of-the-river, resulting in much less environmental impact in comparison to other hydropower developments. This report lists the numerous approvals required from the MNRF, DFO, MOE, and the Municipality following acts such as the Canadian Environmental Protection Act, the Navigable Waters Protection Act, Fisheries Act, etc.

Based on successes from other Micro-hydro dam projects, it is recommended that public participation in key to process, without proper consultations the environmental assessment is not effective.]]>
Host contact: Emmerson, Kim]]> Department: Environmental and Resource Science/Studies]]>